RIVIERA BEACH — The city council voted unanimously Wednesday night to
contribute up to $7 million toward an ocean breakwater designed to
reduce beach erosion on Singer Island.
The vote came in a packed council chambers after some mainland
residents complained that they should not have to help pay for shoreline
protection on the barrier island.
Councilwoman Judy Davis urged all to view the city's needs as a whole
and to move beyond the east-side, west-side rift that has divided some
residents in the past.
"That beach belongs to all of us," Davis said. "Let's move our city
forward in a positive way."
Assistant City Manager Paul White said the city has spent $15 million
over the past four years on improvements to recreation facilities on the
mainland.
Council Chairman Cedrick Thomas said the city would pass a bond issue
large enough that additional money will be available for mainland
projects.
The city's contribution to the breakwater is expected to be $6
million - 20 percent of the $30 million estimated total cost. If
construction costs exceed the estimate, the city could be asked to
contribute up to $1 million more with council approval. The agreement
calls for Palm Beach County to contribute $12.5 million. Another $11.5
million will come from the state.
As designed, the breakwater will run parallel to the beach for a
mile, from the south end of John D. MacArthur Beach State Park to Ocean
Reef Park.
It will consist of 11 wave-breaking structures made of limestone and
granite that rise 1 to 3 feet above the surface in about 12 feet of
water. Gaps will allow swimmers, sea turtles and water to move through.
Although the breakwater is not expected to stop all beach erosion, it
should slow erosion enough that only sand from upland sources will be
needed to maintain beaches behind the breakwater, said Daniel Bates, the
county's environmental director. "We'd be saving a lot of offshore
dredging work," he said.
Beach restoration projects that involve pumping sand from offshore
typically cost around $8 million and must be done every seven years or
so, Bates said.
The project is expected to create 6 acres of hard-bottom habitat
along the ocean floor.
If the county approves the project and permits are secured as
expected, breakwater construction would begin this summer, Bates said.
Similar breakwaters are being considered for the waters south of Jupiter
Inlet and off Lantana Beach.
Also on Wednesday, the council unanimously approved the site plan for
Florida Power & Light Co.'s conversion of its old Riviera Beach power
plant to natural gas.
The power plant conversion, expected to be complete in 2014, would
more than double the plant's generating capacity, to 1,250 megawatts.
Smoke stacks of the new plant will be 157 feet tall, just over half the
height of the existing 300-foot stacks.